How to maintain effectively production Resources (Human) with the respective to absent and leaves. If the Resource is Absent/Leave Master Production scheduling should consider other alternative available resource (human).
I’ve created 2 (A & B) employees and assign to 2 Production resources and created a resource group and added both resources. Created a route and in the lines I’ve assigned resource group and the resource is Quantity 1.
So the system will consider one human resource when running the scheduling.
In case of a production order running for 3 months, in between the (A) resource on vacation for 10 days, system should consider the next available (B) resource is free and consider that resource to be working for 10 days and remaining days will be resource (B).
In AX 2012, Absent is not considering in the capacity planning, so how to effect absent/leave to resource capacity planning.