Hi Experts,
Scenario : Company has two sites S1, S2. Company has product, requires three operations to be performed (O1 & O3 at S1 and O2 at S2).
It seems AX 2012 does not allow to specify operations, using resources from different site, into single route. S2 is not a external vendor or subcontractor hence if possible i would like to refrain using vendor type of work center.