Hello,
Maybe somebody has seen similar issue and found solution already; I worked on 2012R2 installed few months ago, prepared OLAP cubes there and SSAS reporting based on these cubes; all things there worked fine.
Now I am trying to do same on latest 2012R2 (lates binaries); prepared dwproj using AX BI tools, processed it, but when opening (excel or VS) I see that:
- financial dimensions defined in AX are available as cube dimension, but
- none of them contains any value defined for them in AX
- also browsing 'FinancialDimensions..' tables in VS (explore data) I do not see any of values mentioned there
As an example - in dimension 'branch' I have few cities defined in AX; in cube I see only dimension 'branch', but not any of defined values.
Is anybody aware what are/may be differencies done in cube/project structure last weeks/month by MS? I believe it is different, but I have no clue why it was changed.
regards