Hi Experts,
I want system to use relative setup and run time (from operation relation) when system picks alternate work center for scheduling. For example when Item X produced on machine M1, 100 Pcs of Item X can be processed in an hour and on machine M2 200 Pcs can be processed on same time. Both of these machines are having the same capability called 'Packaging'.
I tested this but system when re-schedules on M2, it still takes the setup and run time from production route (defined for M1). Seems, we can not group resources under same capability if their efficiency varies or alternate route is the only option (which requires it to copy manually on production route) ?