I'm experienced in using AX 2009 & 2012 from an accounting standpoint, but very inexperienced from a production standpoint.
What are the internal effects when a production order that is linked to a project is "ended"? Does ending the production order allow all its cost to be applied to the project? I want to make sure I'm understanding things correctly.
Also, for a sales order linked to a project, what happens when the items on the sales order are "shipped off" in the system?
Thank you!
Chad