Hello,
Production order is created for 1000 Nos. on day1
Started with 1000 Nos. day1
Route consist 5 operation, which are completed as under:
Printing 1000 Nos in 8Hrs on day1
Assembly 500 Nos in 8Hrs on day 1 & 500 Nos in 8Hrs on day2
Welding 400 Nos in 8Hrs on day 1, 400 Nos in 8Hrs on day2 & 200 Nos in 4Hrs on day3
Testing 1000 Nos in 4 Hrs on day4
Packing 1000 Nos in 4 Hrs on day4
Kindly explain how should I post route journal date wise. Each operation started & ended on different dates.