Dear All,
We are facing an issue in the timesheet synchronization from AX to project Server. The issue is that when the timesheets are posted in the AX and then automatically synched to the PS, the hours transferred are always 0 (zero). Any idea?
We are using the VM provided by Microsoft which comes with pre-configured Project Server, AX and Enterprise Portal. We setup the integration b/w the AX and PS using the manual and it was setup successfully, we are able to synchronize Projects and resource and WBS b/w both seamlessly. The only problem is that it just doesn't synch the timesheet hours to the actual work in the Project Server.
We also noticed that in AX when we open up details of a WBS it shows the impact of timesheet hours in "Realized Finished" field of the Project section, but it shows 0 in "Actual work & total work" fields of the "Detail" section.
I have also attached images for further clarification.
Project Server Timesheets from AX
Any help would be highly appreciated.
Regards,
Khalid