I am new to the AXUG, and my company is implimenting AX 2012.
Our organization would like to forecast items at the finished good level for our build-to-order products in order to produce bom-line requirements for raw materials planning, but we do not want to schedule the finished products until we get actual customer demand.
How can we set our planning parameters to ignore the forecast for planned orders at the finished level, but still explode the forecast through to the lower level requirements? Or how can we filter planned production orders to filter out the forecast demand from actual customer demand and segregate the build-to-order products from build-to-stock ones?
Thank you,
Leif