I have a couple of questions about data upgrades from Ax 2009 to Ax 2012
Firstly, the system we intend to upgrade has been heavily bespoked but the plan is to drop the majority of the bespoke functonality in favour of standard Ax.
However some of the key data fields we would like to migrate to Ax 2012. So we intend to create those few fields in Ax 2012 and leave the others out completely that we are not interested in.
Will the bulk copy process handle copying of the data for tables where some fields present in Ax 2009 are not even in the Ax 2012 table?
Will it generate errors or just ignore the fields that are not present in the Ax 2012 target system?
Secondly, there is some data where the table in Ax 2009 is bespoke but there is now an equivalent table in Ax 2012.
What approach should I use to get the new Ax 2012 table populated with the contents of the bespoke table in Ax 2009?
Thanks
Ian